Countdown Begins: New Rail Bridge Paves Way for Botley Road Reopening
The installation of a new rail bridge marks a significant milestone in the upgrade of Oxford rail station, part of a £237 million project aimed at enhancing regional transport infrastructure. The Botley Road, closed since early 2023, is expected to reopen by the end of August 2026.
Significant Developments in the Upgrade Project
The completion of the bridge occurred after a week-long closure of the rail lines in Oxford. This was necessary for contractor Kier to safely dismantle the old bridge and install the new spans. The project recently achieved its goal, allowing the station to fully reopen.
Praise for Successful Execution
Former Lord Mayor John Tanner commended the contractors, recognizing their efforts as “remarkable.” He highlighted the challenges overcome during this process and noted the effective installation of the new bridge.
- Week-long rail line closure for installation
- Safe demolition of the old bridge
- Installation of new bridge spans completed
With the temporary walkway diversion through Oxford station now closed, passengers can return to using the usual route beneath the new bridge. Rail services between Oxford and Didcot Parkway have normalized, following the previous reliance on replacement bus services.
Benefits of the New Rail Bridge
The new bridge will not only accommodate an additional line but will also facilitate a new Platform 5. This enhancement is crucial for improving the East West Rail links and supporting the future reopening of the Cowley Branch Line for passenger use.
Giles Clark, the principal programme sponsor for Network Rail, noted the importance of completing this phase on schedule. He expressed gratitude to all those involved in the project and emphasized the significance of these improvements for passenger safety and reliability.
Looking Ahead to Botley Road Reopening
The reopening of Botley Road is anticipated to alleviate traffic congestion in Oxford. Tanner praised both the Rail Minister, Lord Hendy, for reviving a previously stalled scheme and the overall collaboration among the engineers and workers on-site.
| Key Details | Date | Cost |
|---|---|---|
| Start of Botley Road Closure | Early 2023 | £237 million upgrade project |
| Anticipated Reopening | August 2026 |
The railway station upgrade has faced various delays, causing the project’s budget to increase from £161 million to £237 million. Construction of a new western entrance to the station remains ongoing.